The two-side traffic under one of the overpasses on Yerevan-Artashat M6 highway is announced open
12-05-2017
The construction works of the overpass of Ayntap community will still continue on the mentioned section of the highway with open traffic. Now 3 out of 8 overpasses, which are being constructed/renovated on Yerevan-Artashat highway, are open for two-sided traffic, but the civil works on are still ongoing. The open overpasses are those of Dimitrov and Araksavan, Burastan and now also Ayntap communities. Traffic under the remaining 5 overpasses will be restored by May 25. Overall the construction works will finish by the end of September.